implementation
Duration: 8 June 09 - 2 July 09
Participants: Holografika, TID, Bilkent
In this sprint, rendering engine is updated. New widget classification is done. UML of the UI Library is redesigned and updated.
Demo: 3 July 09

Duration: 15 May 09 - 4 June 09
Participants: Holografika, TID, Bilkent
This sprint is after the project’s review. Thus, it is a test/review/check sprint. Moreover, the touch sensor is integrated to the event system and ported to OMAP Zoom.
Demo: 5 June 09

http://the3dphone.eu./images/s2.1.png
Duration: 17 March 09 - 27 March 09
Participants: Holografika, TID, Bilkent, HHI
This sprint is before the project’s review. Thus, it is an integration and minor changes sprint. The addressbook application is completed and all applications are ported to OMAP Zoom. In addition to this, we have some sensor based applications running on UMPC, Touch application and Stereo Proccessin applications.
Demo: 30 March 09
Duration: 12 Feb 09 - 16 March 09
Participants: Holografika, TID, Bilkent
In this sprint, some applications such as gallery, 3D addressbook, StereoVideoPlaybackApp are implemented and Rendering team implemented some material properties and texture mapping to SceneGraph. For input side, team stated some basic gestures such as left, right,up and down with sensor and they made a demo that showed the interaction on UMPC.
Demo: 16-18 March 09
Duration: 19 Jan 09 - 06 Feb 09
Participants: Holografika, TID, Bilkent, Streamezzo
More work is done in the 4th sprint. Widget design and implementation was carried on, receiving keypad events was implemented, scenegraph pickray and animation classes have been implemented and gestures were specified for sensor and camera inputs.
Demo: 9-10 Feb 09
Duration: 17 Dec 08 - 14 Jan 09
Participants: Holografika, TID, Bilkent, Streamezzo
In the 3rd sprint; 3D lenticular display software is developed, design and implementation of UI widgets started, scenegraph phase III which consists of performing visibility tests during rendering is completed and build bot for development process is setup.
Demo: 15-16 Jan 09
Duration: 24 Nov 08 - 15 Dec 08
Participants: Holografika, TID, Bilkent, Streamezzo
In this second sprint, scenegraph phase II, event system, 3DUI Components’ design and some study on GStreamer were kept on.Second sprint is more successful than the first one.
Demo: 15-17 Dec 08


Duration: 20 Oct 08 - 14 Nov 08
Participants: Holografika, TID, Bilkent
In this first sprint, scenegraph phase I, application manager and some plugins are implemented.. As this is the first sprint, team started to feel the team spirit and familiarize the agile process..
Demo: 14-18 Nov 08


3DPhone Implementation Team uses agile approach for development. Here, you’ll find some information about agile process.
Agile processes are iterative processes that use specific project management and software engineering practices to sustain the delivery of new software functionality every one to four weeks.
Agile Manifesto Values:
- Individuals and interactions over processes and tools
- Working software over comprehensive documentation
- Customer collaboration over contract negotiation
- Responding to change over following a plan
Why adopt Agile processes?
- Reduced time-to-market.
- Increased innovation.
- Business alignment.
- Increased quality.
- Reduces product and process waste.
- High visibility and control over the project progress.
- Empowered, motivated and self organizing Teams.
You can find more information about Agile Process below: